1. Construction of Flats at Nanak Nagar (PANCHVATI APARTMENTS) 1199   359.29 120 400 Blocks B,C and D complete except painting and plinth protection. Block A upto Ist floor and block E upto 2nd floor.  
2. Tawi River Front Development.              
3. Construction of Media Centre at RHC. 315 866.56 40.57 40 145 Earth work completed. Peripheral RCC basement wall about 200 rft completed.  
4. Construction of Housing and UD complex across Railway Line at Bahu Fort. 232 287 47.11 70 168.21 Structural Work completed.  
5. Renovation of Bahu Fort 69.50   25.20 28.17 19.50 Repair of main entrance (Deodi) and coping of wall completed.  
6. Construction of bus terminal at Transport Nagar. 134.75            
                 
Projects of Division Number II
Sno. Name of Project
AAA(Rs. in Lac)
Exp. Ending 03/2008
Proposed Outlay
Physical Progress Remarks
Original Revised 2008-09 2009-10
1. Construction of Hostel for Ladhaki Girls students at EWS Colony. 119.08   60.55     Sper structure completed. Finishing work like plastering, flooring in progress.  
2. Construction of office complex of Accounts and Treasuries at Muthi. 423.30   127.13        
3. Construction of idle parking yard for Banihal route buses at Khanpur Nagrota. 670.50   201.44    

Approach Road: Drainage crossing completed, earth work in progress. Earth work, shingle metal, premix carpet under layer, channeliser, breast wall and side drain completed in Yard No. I.

 
4. Development of parking at Prem nagar near Samadian. 39.75   28.39     Work completed except premixing, fencing, painting and fixing of barrier.  
5. Construction of community hall in Dogra Khatri Sabha near old GPO Pacca Danga. 27.00   2.40     Dismantalling/earth work in progress.